Scheduling a holiday or non-working days is extremely important when managing projects because each day can have an impact on the outcome of your project. 
Luckily, Instagantt makes it very easy to highlight these special occasions. 
In order to do so, hover your cursor over an empty space for the date, and right-click on it. Once the dialogue appears, choose the Highlight day as holiday option from the menu. Name the holiday, select It’s a non-working day (holiday) from the drop-down menu, and choose a color to highlight your date.

To modify or delete a highlight, head over to the timeline and move the arrows to expand or reduce the date range for the highlight, or click on the trash bin icon to remove it completely.