Instagantt University
Upload your Project's Tasks with CSV File Imports

Import CSV

Already had some projects you need to keep working on? Instagantt makes it easy to reduce setup time by allowing you to import a CSV file with existing information of a project you're working on. Head over to the Options menu and scroll down to + Import CSV button. 




This option will let you download an example CSV file to populate it with your tasks and upload it to Instagantt. Bear in mind that the import file is very sensitive to the format of the cells! We highly recommend populating the template to avoid any format discrepancies that could affect the process!

This is how the example file looks:

In Apple Numbers

In Microsoft Excel